I-75 Mill Creek Expressway


Home
About the Project
Members
Schedule
Archive
Alternatives
Related Links
FeedBack
Contact Information
FAQ

Welcome to the I-75 Mill Creek Expressway project website!

January 2017 Update:

Overall Project Update


Corridor Project Phasing and Schedule

Due to cost, constructability, and time constraints, the Mill Creek Expressway project has been split into eight phases of construction. The following table provides a brief description of each phase, major milestone dates, and current status:

Phase

Project Description

Construction Cost
(million)

Right-of-Way Acquisition
Start

Construction Start

Construction End

1

Mitchell Ave. Interchange

$53.6

Completed

Started

Completed

Status

Project is complete.

2

Monmouth St. Overpass

$6.8

Completed

Started

Completed

Status

Project is complete.

3

Colerain/Beekman/I-74 Interchange

$13.1

Completed

Started

Completed

Status

Project is complete.

4

I-75 from the Western Hills Viaduct to Monmouth overpass (includes the Hopple St. interchange)

$90.8

Completed

Started

July 2017

Status

Current work includes widening and rehabilitation of I-75 pavement, I-75/Hopple St. interchange improvements and bridge construction. 

The following detours/MOT restrictions are in place on the project:

  1. Eastbound Hopple to Northbound IR75 Ramp Closure: 
    • Detour is EB Hopple to Connector Road to NB Central Parkway to NB IR75 via ramp by Cincinnati State
  2. Eastbound Hopple to Southbound IR75 Ramp Closure: 
    • Detour is SB on Colerain Avenue to EB on Marshall Avenue to NB on Central Parkway to EB on the Connector Road to WB on Hopple to SB75 via ramp
  3. MLK is permanently closed at the intersection of Central Parkway and Hopple:
    • Detour is the new Connector Road
  4. Bates Avenue ramp to IR74W is permanently closed:
    • This ramp was replaced by the ramp from the Hopple Bridge to IR74W.
  5. IR74E ramp to Central Parkway is permanently closed:
    • Detour is to Hopple Street Exit from SB75
  6. IR74W is reduced to one lane for 120 days at the IR75/IR74 Interchange.

I-75 mainline traffic was switched into Phase 6 in June 2016.  The current traffic pattern for this phase is as follows.  Four lanes of I-75 northbound are being maintained with three lanes on the west side of I-75 in a contra-flow configuration.  Four lanes of I-75 southbound traffic still remain shifted to the west side of I-75. Northbound I-75 will be reconstructed in this phase.  Phase 6 is anticipated to be complete in November 2016. 

5

I-75 from Monmouth Overpass to Mitchell Ave. (includes I-74 Interchange and I-74 improvements)

$161.0

Started

Unscheduled

Unscheduled

Status

Final plan design activities are in progress. Current design is approximately 90% complete. Final plans are due to be completed by May 2016. R/W Acquisition is scheduled for completion by June 2015.

6

Replacement of RR Overpass South of Norwood Lateral

$18.1

Started

Started

September 2016

Status

Railroad bridge is complete with exception of girder painting above the center pier. Painting operations should complete by 10/24/16. Both railroad tracks are in their final configuration and are open to rail traffic.

7

I-75 Mainline from Mitchell Ave. to the Norwood Lateral

$31.2

Started

Started

June 2018

Status

Project entered Phase 3 MOT alignment on 12/21/16. SB & NB (3 lanes each direction) are running bi-directional on future (finish condition) SB75. Phase 3 construction will begin 1/9/17. Phase 3 will consist of new pavement construction of NB75 from MM 6.7 to MM 7.9. Included in this work is the construction of the Vine St overpass bridge for future NB75 lanes. Sound walls will also be constructed during Construction Phase 3. Completion date is still scheduled for 9/30/17

8

I-75 Mainline from the Norwood Lateral to Cross County Highway

$113.7

December 2013

Unscheduled

Unscheduled

Status

Current design is approximately 95% complete. R/W acquisition is nearly complete.

8a

Seymour Avenue Overpass

$8.5

August 2013

April 2017

November 2017

Status

Final plans are complete. R/W acquisition has begun and is on schedule.

9

Building Demolition Hopple/Colerain/Beekman Areas

$1.8

N/A

Started

Completed

Status

Project is complete.

 

Project Contact Phases 2, 6, 7, and 9:
Joe Smithson, P.E.
The Ohio Department of Transportation, District 8
505 South SR 741
Lebanon, Ohio 45036
Phone: 513-933-6707
Email: Joe.Smithson@dot.ohio.gov

Project Contact Phases 1, 8,  and 8a:
Rick Hively, P.E.
The Ohio Department of Transportation, District 8
505 South SR 741
Lebanon, Ohio  45036
Phone:  513-933-6600
Email:  rick.hively@dot.ohio.gov

Project Contact Phases 4 and 5:
Lee Matthes, P.E.
The Ohio Department of Transportation, District 8
505 South SR 741
Lebanon, Ohio  45036
Phone:  513-933-6612
Email:  lee.matthes@dot.ohio.gov

Project Contact Phase 3:
John Otis, P.E.
The Ohio Department of Transportation, District 8
505 South SR 741
Lebanon, Ohio  45036
Phone:  513-933-6199
Email:  John.Otis@dot.ohio.gov

Revive Cincinnati Effort:

ODOT is participating and assisting this City-led effort by providing information on our projects in the Hamilton I-75 corridor. As results and recommendations are adopted by the City, ODOT will work with the various partners to incorporate them when feasible.

 

 

 
   

What's  New?

Construction Information

now available.

Click link above for details...
________________

   
 


I-75 and Paddock
(photos by Larry Stulz)


I-75 & I-74

(photos by Larry Stulz)


Norwood Lateral

(photos by Larry Stulz)


Home | About the Project | Members | Schedule | Archive | Alternatives | Related Links | FeedBack | Contact Information | FAQ | Construction Information

  Copyright 2013 TranSystems Corporation. All rights reserved.
For problems or questions regarding this Web site contact HAM75Webmaster@transystems.com.
Last updated: 01/22/13.