I-75 Mill Creek Expressway


Home
About the Project
Members
Schedule
Archive
Alternatives
Related Links
FeedBack
Contact Information
FAQ

Welcome to the I-75 Mill Creek Expressway project website!

April 2018 Update:

Overall Project Update


Corridor Project Phasing and Schedule

Due to cost, constructability, and time constraints, the Mill Creek Expressway project has been split into eight phases of construction. The following table provides a brief description of each phase, major milestone dates, and current status:

Phase

Project Description

Construction Cost
(million)

Right-of-Way Acquisition
Start

Construction Start

Construction End

1

Mitchell Ave. Interchange

$53.6

Completed

Started

Completed

Status

Project is complete.

2

Monmouth St. Overpass

$6.8

Completed

Started

Completed

Status

Project is complete.

3

Colerain/Beekman/I-74 Interchange

$13.1

Completed

Started

Completed

Status

Project is complete.

4

I-75 from the Western Hills Viaduct to Monmouth overpass (includes the Hopple St. interchange)

$90.8

Completed

Started

Completed

Status

Project is complete.

5A

I-75 from Monmouth Overpass to Mitchell Ave. (includes I-74 Eastbound Interchange ramps)

$70.1

Started

Fall 2018

Fall 2021

Status

Project has been broken out into two parts labeled 5A and 5B.
-HAM-75-3.85; PID 83723: MCE phase 5. Project covers design and r/w acquisition for phases 5A and 5B.
-HAM-75-3.84; PID 104667: MCE phase 5A. Two step Design-build project to construct a portion of PID 83723 plans, focused on I-75 mainline. To be awarded on 7/9/18.

5B

I-74 from Colerain/Beekman Interchange to I-75 (includes I-74 Westbound Ramps)

$81

Started

Unscheduled

Unscheduled

Status

HAM-74-18.01; PID 104668: MCE phase 5B. Project addresses remaining work not addressed with phase 5A. No committed sale date.

6

Replacement of RR Overpass South of Norwood Lateral

$18.1

Completed

Started

Completed

Status

Project is complete.

7

I-75 Mainline from Mitchell Ave. to the Norwood Lateral

$31.2

Completed

Started

June 2018

Status

The major project work items are complete. Interstate 75 is currently operating in the final configuration with all lane additions. Permanent pavement striping is to be completed in Spring 2018 from Mitchell Avenue to SR 562 (Norwood Lateral). Other minor weather dependent items to be completed in Spring of 2018 include final concrete sealing, noise wall panel closure, retaining wall extension, and median light tower erection. The project completion date is estimated to be June of 2018.

8

I-75 Mainline from the Norwood Lateral to Cross County Highway

$119.6

July 2015

Spring 2022

Spring 2025

Status

Current design is complete; minor updates to the plans will be made in 2018. R/W acquisition is nearly complete.

8a

Seymour Avenue Overpass

$8.5

Completed

April 2017

June 2019

Status

Current work is focused on the substructure units of the first phase of the Seymour bridge. The second major maintenance of traffic phase on I-75, relocating traffic to the outside edges of the I-75, will be implemented in April 2018. The traffic switch will permit completion of the first phase of the bridge. Phase 1 of the bridge construction will be in place through November 2018, weather depending. The project will then build the second half of the Seymour substructure. The second phase of bridge work will require traffic to be moved towards the center of I-75. Phase 2 of the bridge construction will begin in early 2019 with superstructure work to follow in spring 2019. The Project is moving towards completion in June of 2019.

9

Building Demolition Hopple/Colerain/Beekman Areas

$1.8

N/A

Started

Completed

Status

Project is complete.

 

Project Contact Phases 2, 6, 7, 8a and 9:
Joe Smithson, P.E.
The Ohio Department of Transportation, District 8
505 South SR 741
Lebanon, Ohio 45036
Phone: 513-933-6707
Email: Joe.Smithson@dot.ohio.gov

Project Contact Phase 8:
Stephanie Roth, P.E.
The Ohio Department of Transportation, District 8
505 South SR 741
Lebanon, Ohio 45036
Phone: 513-933-6584
Email: Stephanie.Roth@dot.ohio.gov

Project Contact Phase 4:
Lee Matthes, P.E.
The Ohio Department of Transportation, District 8
505 South SR 741
Lebanon, Ohio  45036
Phone:  513-933-6612
Email:  lee.matthes@dot.ohio.gov

Project Contact Phases 5A, 5B:
Charlie Rowe, P.E.
The Ohio Department of Transportation, District 8
505 South SR 741
Lebanon, Ohio 45036
Phone: 513-933-6596
Email: Charles.Rowe@dot.ohio.gov

Project Contact Phases 1, 3:
John Otis, P.E.
The Ohio Department of Transportation, District 8
505 South SR 741
Lebanon, Ohio  45036
Phone:  513-933-6199
Email:  John.Otis@dot.ohio.gov

Revive Cincinnati Effort:

ODOT is participating and assisting this City-led effort by providing information on our projects in the Hamilton I-75 corridor. As results and recommendations are adopted by the City, ODOT will work with the various partners to incorporate them when feasible.

 

 

 
   

What's  New?

Construction Information

now available.

Click link above for details...
________________

   
 


I-75 and Paddock
(photos by Larry Stulz)


I-75 & I-74

(photos by Larry Stulz)


Norwood Lateral

(photos by Larry Stulz)


Home | About the Project | Members | Schedule | Archive | Alternatives | Related Links | FeedBack | Contact Information | FAQ | Construction Information

  Copyright 2013 TranSystems Corporation. All rights reserved.
For problems or questions regarding this Web site contact HAM75Webmaster@transystems.com.
Last updated: 01/22/13.